FAR 7.203

Solicitation provision.

Contracting officers shall insert the provision at 52.207-4 , Economic Purchase Quantity-Supplies, in solicitations for supplies. The provision need not be inserted if the solicitation is for a contract under the General Services Administration’s multiple award schedule contract program, or if the contracting officer determines that- (a) The Government already has the data; (b) The data is otherwise readily available; or (c) It is impracticable for the Government to vary its future requirements.

Source: acquisition.gov — FAR