DFARS 242.1107
Contract clause.
(b) When using the clause at FAR 52.242-2, include the following instructions in the contract schedule— (i) Frequency and timing of reporting (normally five working days after each reporting period); (ii) Contract line items, exhibits, or exhibit line items requiring reports; (iii) Offices (with addressees/codes) where reports should be sent (always include the contracting office and contract administration office); and (iv) The following requirements for report content— (A) The problem, actual or potential, and its cause; (B) Items and quantities affected; (C) When the delinquency started or will start; (D) Actions taken to overcome the delinquency; (E) Estimated recovery date; and/or (F) Proposed schedule revision.